Bathroom Renovation Order of Works: Trade by Trade
The exact sequence a bathroom renovation runs in, which trade does what, and why the order cannot be rearranged to save time.
6 August 2026 • 3 min read
A bathroom has more trade dependencies packed into a small room than any other part of a house. The order is not a preference, it is a chain where each link needs the one before it finished.
1. Strip out
Everything out, back to frame or slab. Tiles, fixtures, wall sheeting, and usually the floor screed.
This is the discovery stage. Whatever is wrong behind the walls, this is when it appears: rot in the framing, corroded pipework, non-compliant wiring, an out-of-level floor. Any of it has to be dealt with before the sequence continues.
2. Plumbing rough-in
The plumber sets out drainage and supply lines while the walls and floor are open.
If the layout is changing, this is where that work happens. Moving a toilet or shower waste is a rough-in job, and once the sheeting is on, changing your mind means opening it back up.
3. Electrical rough-in
Cabling for lighting, exhaust fan, heated towel rail, underfloor heating and power. Same principle: it has to be in the wall before the wall closes.
Underfloor heating is worth deciding now. Retrofitting it means lifting the floor.
4. Sheeting
Wet area wall sheeting fixed and set. Suitable board, correctly fixed, joints treated.
This is the substrate the waterproofing bonds to. Water-resistant sheeting is not waterproofing, it is the surface waterproofing goes on.
5. Screed and falls
The floor screed establishes the falls to the waste so water actually drains. Get this wrong and the shower ponds for the life of the bathroom, which no membrane fixes.
6. Waterproofing
Primer, reinforcement at junctions and penetrations, membrane coats, then a full cure. The full sequence is here.
Nothing happens in the room during the cure. This is the stage that gets squeezed when a job is behind schedule, and squeezing it is the most common reason wet areas fail.
7. Tiling
Floor first or walls first depends on the setout and the tiler. Either way, this is where the room starts looking like a bathroom.
Time here is driven by cuts, not area. Niches, hobs, penetrations and mitred external corners are what take the hours.
8. Grouting
Then the grout cures. It needs longer than most people expect before the room is wet.
9. Plumbing and electrical fit-off
Both trades return. Toilet, vanity, tapware, shower fittings connected and tested. Lights, fan and heating connected and tested.
This is the second visit for each, which is why trade availability affects a bathroom more than most rooms.
10. Silicone
Internal corners and the wall-to-floor junction get silicone rather than grout, because those junctions move and grout cracks when it is asked to flex.
Silicone needs to cure before the shower is used.
11. Shower screen and final fit
Usually measured after tiling, because it has to fit the finished opening rather than the framed one. That means a wait between tiling and installation on many jobs.
Why the order cannot be changed
Every stage depends on the last: rough-in has to precede sheeting, sheeting precedes waterproofing, waterproofing precedes tiling, tiling precedes fit-off.
You cannot buy speed by adding people to a bathroom either. It is one room, and stages like the membrane cure take the same time regardless of how many are standing in it. The realistic timeline is 2 to 3 weeks.
If you would rather one party sequenced and scheduled all of it, that is what our renovation packages cover.
Common questions
What order do trades work in on a bathroom renovation?
Strip out, plumbing and electrical rough-in, sheeting, screed, waterproofing, tiling, grouting, then plumbing and electrical fit-off, then silicone. Each stage depends on the one before it being complete.
Does the plumber come before or after the tiler?
Both. The plumber does rough-in before sheeting, so pipework is inside the wall, then returns after tiling for fit-off to connect the fixtures. The same applies to the electrician.
Can tiling start before waterproofing is finished?
No. The membrane goes on before tiles and must be fully cured first. Tiling over an uncured membrane traps moisture underneath and is a leading cause of wet area failure.
More on planning a renovation
Full guidePlanning a Bathroom Renovation: A Complete GuideWant this done properly the first time?
We have been tiling and renovating bathrooms across Sydney for 28+ years. Fixed quotes, no surprises, and the wet areas done to the standard.